Updated Jan. 29th

EXCELSIOR EXPANSION UPDATE – January 29th

Holy cow…those walls came down fast. For those unaware, we began knocking down walls in our building 8 days ago. The adjacent space quickly went from two separate entities (one an auto shop, another a storefront) into one massive/awesome space. After stripping away the stucco, insulation and wall coverings we were left with gorgeous red brick, windows just begging to see the light of day and a ceiling with as much history as Excelsior itself.

To give you some more perspective, check out the first couple days of demolition below

From Day 1 of Demo to Day 3, we saw massive changes.

From Day 1 of Demo to Day 3, we saw massive changes.

As of now, we are still on pace to have the new taproom open to the public in late April/early May. We are also still on track to get 12 oz. bottles on shelves around May 1st as well. We’re obviously excited about our soon-to-be ability to get beer to more and more folks in the Metro, but in the meantime make sure to check out www.excelsiorbrew.com/locations for information on where to find our beer currently.

Thanks again to the folks who helped get us to where we are and the people involved in our expansion. Things are getting real here at the brewery, stay tuned for more updates!